You are working on a hybrid cloud project, where production applications (yet to be fully developed) are to be deployed.Which of the following is a project requirement?
A. The production data must be in the UK at all times.
B. The hosting partner provides sufficient resources without overcommitment to support application load.
C. The hosting provider meets uptime expectations.
D. The development team provides the software on time.
Answer : A
A. The production data must be in the UK at all times.
B. The hosting partner provides sufficient resources without overcommitment to support application load.
C. The hosting provider meets uptime expectations.
D. The development team provides the software on time.
Answer : A